Enterprise Calendar
Permissions
● Only team administrators can adjust project working hours
● [Attention] Modifying the team's Enterprise Calendar will automatically adjust the scheduled time of all tasks in the system, and all team members will be notified
Operation Path
● Enter [Settings] - [Function Configuration] - [Enterprise Calendar]
Workday
● The Workday can be selected accordingly.
● After setting work days and rest days, rest days will be automatically skipped from the scheduled tasks in the project
Holidays
-
Holidays take precedence over selected work days.
Working hours
● By default, two working periods are displayed- morning and afternoon. The time for this two periods can not be overlapped
● Select the start and end time for the task, the working time will be automatically set depending on the business calendar setting. the Working time can be modified manually later.
Duration
Concepts of working hours and duration
● Working hours: the working time of each individual;
● Duration: the actual time it takes to complete each project task
Set the duration
● Select [When the work calendar changes, the start and end time of the task plan remain unchanged, and the duration length is automatically adjusted] or
[When the work calendar changes, the duration length remains unchanged, and the task deadline is automatically adjusted] accordingly.
● After turning it on, the duration of the task can be seen at the schedule of the task.
Exception date
● The priority of the exception date is higher than all date and time settings
● The exception calendar can force rest/ work days in a certain time period to be changed to work/ rest days
● The exception date has a fold mark in the upper right corner of the calendar date